Government of Nepal
Ministry of Water Supply
Water and Sewerage Management Department
Federal Water Supply and Sewerage Management Project, Dhankuta
Notice of Intention to Accept Bid
Publication date: 2081/11/21
According to the decision of the evaluation committee, among the bids that were received online within the specified period, as per the notice of invitation of bids published in the Solar National Daily on 2081/09/26 and on 2081/09/29 and on 2081/09/29 and Himalayan Times National Daily on 2081/10/13, the bids of the bidders as per the schedule were selected for approval as the minimum evaluation was considered effective. For the purposes of section 27 (2) and section 47, a notice of intention to accept the bid has been published for 7 (seven) days.
Details:
C. No.
1
Bid No
Rede
Job description
Name and address of successful bidder
Accounts Payable (including VAT and P.S.)
FWSSMP/Dhankuta/NCB/Works-04/2081/082
Construction Works of Nigale Sijalitole School Danda Phabre Kintang Water Supply Project, Dhankuta
BNK-Mahalakshmi JV, Dhankuta
2,83,50,760.15
FWSSMP/Dhankuta/NCB/Works-05/2081/082
Construction of Tamor Chuliban, Rudrabari, Khurila, Guthitar, Dhodeni, Debitar, Belahara, Belahara Besi, Dumre WSP, Dhankuta
BNK-Mahalakshmi JV, Dhankuta
3,43,96,595.45
FWSSMP/Dhankuta/NCB/Works-07/2081/082
Construction Works of Phalametar Pakchuwa Dumre Tallo Iname Tintale Khorkhole Siddhiban (Basnetdanda Tank Nirman) Water Supply Project
T.K. Engineering and Construction Suppliers Pvt.Ltd, Kohalpur-07, Banke
2,05,04,269.86
to God
4
FWSSMP/Dhankuta/NCB/Works-08/2081/082
Construction Works of Jimigaun Dhodeni Olangtar Malbase Phedi Sisne Garjuwa Sisne Neguwatar Kamicha Thapechuwa Hattikhor Badhuwa Tangkera Water Supply Project
T.K. Engineering and Construction Suppliers Pvt.Ltd, Kohalpur-07, Banke
2,10,83,937.82
5
FWSSMP/Dhankuta/NCB/Works-09/2081/082
Construction Works of Besrang Katahare Dharapani Burjakhola Belarang Water Supply Project
T.K. Engineering and Construction Suppliers Pvt.Ltd, Kohalpur-07, Banke
2,17,66,646.53
6
FWSSMP/Dhankuta/NCB/Works-18/2081/082
2
3
Construction Works of Tintale Lungdhang Wakti Durumtar Tribhungkhola Chhapauli Takure Kagune Lalahang Lalahani Selele Burkha Water Supply Project, Dhankuta
Team-Swastika JV, Sunsari
95,44,214.86
K